• Jan De Nul cable Northwind
  • Jan De Nul cable Northwind
  • Jan De Nul cable Northwind
  • Jan De Nul cable Northwind
  • Jan De Nul cable Northwind

Northwind, storage of the electrical cable

A 43 km, 245 kV connection from Northwind to Zeebrugge. De rest of the cable is stored in Port of Oostende.

Project Description

The rest of the electrical cable which connects the Northwind wind farm with the main land is stored in the Port of Oostende.

Project Details

The cable arrived at quay 501 in the Zeewezendok. Transport and loading were organized by Jan De Nul.

  • arrived on pontoon transported on site on spmt's
  • stored on the site of Multitech